Sidewalk Excavation & Trench Installation This Week on Mt. Auburn Street

More sidewalk excavation this week on Mt. Auburn Street, and trench installation for drainage and trees are also planned. See more information in the announcement from the City of Watertown, below. Sidewalk Excavation Continues At Cambridge Line

Excavation of the eastbound sidewalk and curbing on Mount Auburn Street between Belmont Street and Arlington Street will continue on Monday, October 20, 2025 from 7:00 a.m. to 3:30 p.m. Learn about travel and parking impacts below. Traffic and Sidewalk Impacts

The eastbound sidewalk will be closed for excavation starting on Monday, October 20, 2025 at 7:00 a.m. A bypass sidewalk on the eastbound side will be opened up while this work is being completed.Traffic on Mount Auburn Street will be narrowed and you can expect lane shifts, however traffic will be maintained in both directions. Entrances to driveways and parking lots will be maintained.

Mt. Auburn St.: Construction Continues in East End in Area of Coolidge Square

Sections of Mt. Auburn Street in and around Coolidge Square will be under construction this week beginning Monday. See the impacts on traffic, parking, and sidewalks in the announcement from the City of Watertown below. Sidewalk Excavation Continues At Cambridge Line

Excavation of the eastbound sidewalk and curbing on Mount Auburn Street between Belmont Street and Arlington Street will continue on Monday, October 13, 2025 from 7:00 a.m. to 3:30 p.m. Learn about travel and parking impacts below. Traffic and Sidewalk Impacts

The eastbound sidewalk will be closed for excavation starting on Monday, October 13, 2025 at 7:00 a.m. A bypass sidewalk on the eastbound side will be opened up while this work is being completed.

Sidewalk and Road Work Will Impact Coolidge Square, East Watertown This Week

The Mt. Auburn Street project continues with sidewalk work from near the Cambridge line to Arlington Street, while drainage work will take place in Coolidge Square. See details in the announcement provided by the City of Watertown. Sidewalk Excavation Begins At Cambridge Line

Excavation of the eastbound sidewalk and curbing on Mount Auburn Street between Belmont Street and Arlington Street will begin on Monday, October 6, 2025 from 7 a.m. to 3:30 p.m. Learn about travel and parking impacts below. Traffic and Sidewalk Impacts

The eastbound sidewalk will be closed for excavation starting on Monday, October 6, 2025 at 7 a.m. A bypass sidewalk on the eastbound side will be opened up while this work is being completed.

Removal of Pavement on Mt. Auburn St. Begins This Week

The process of removing the old asphalt to prepare for the repaving of on Mt. Auburn Street will begin this week. Also, hydrant installation and sidewalk pouring will take place in the East End. See details in the City of Watertown’s announcement, below. Sidewalk Concrete Installation and Excavation

Sidewalk concrete installation and pouring will take place on the westbound side of Mount Auburn Street, between Belmont Street and Prentiss Street from 7:00 a.m. to 3:30 p.m. Concrete pouring is scheduled to take place between Belmont Street and Prentiss Street on Monday, September 15, 2025.

This Week’s Mt. Auburn St. Construction Begins After Labor Day

Construction on Mt. Auburn Street will take a day off for Labor Day, and resume with sidewalk and drainage work on Tuesday. See more information in the announcement from the City of Watertown. Sidewalk Concrete Installation

Sidewalk concrete installation and pouring will take place on the westbound side of Mount Auburn Street, between Belmont Street and Keenan Street from 7:00 a.m. to 3:30 p.m. Concrete pouring is anticipated to begin between Belmont Street and Francis Street on Wednesday 9/3/2025. Notices have been provided to the properties directly affected within the pouring area.

Sidewalk Construction Continues on One Side of Mt. Auburn Street

Work this week on the Mt. Auburn Street Project includes construction of sidewalks and drainage work in the East End of town. See more information from the City of Watertown below. Curb Installation & Sidewalk Concrete Pouring

Curb installation and sidewalk concrete pouring will take place on the westbound side of Mount Auburn Street, between Belmont Street and Keenan Street, on Monday, August 25, 2025, from 7:00 a.m. to 3:30 p.m. Details on travel and parking impacts are provided below. Traffic and Sidewalk Impacts

The westbound sidewalk will be closed for curb installation and sidewalk concrete pouring starting Monday, August 25, 2025 at 7:00 a.m. A bypass sidewalk on the westbound side will be opened up while this work is being completed.Traffic on Mount Auburn Street will be narrowed and you can expect lane shifts, however traffic will be maintained in both directions. Entrances to driveways and parking lots will be maintained.

Sidewalk Work Continues Along Mt. Auburn St. During Week of Aug. 11

Over the week of Aug. 11 to 15, 2025, the Mt. Auburn Street Project includes sidewalk excavation, as well as drainage installation in the Eastside of town. See details in the announcement from the City of Watertown, below. Sidewalk Excavation Continues

Excavation of the westbound sidewalk on Mount Auburn Street between Belmont Street and Keenan Street will continue Monday, August 11, 2025 from 7:00 a.m. to 3:30 p.m. Learn about travel and parking impacts below.