Mt. Auburn Project: April 9-14 – Traffic & Pedestrian Signal Electrical Work

During the week of April 14-19, 2025, work on Mt. Auburn St. Project includes traffic signal work at two main intersections in East Watertown. See details in the announcement sent out by the City of Watertown. Intersection of Mount Auburn Street & Arlington Street 

Electrical Traffic and Pedestrian Signal Work

Starting Monday April 14, 2025 Newport Construction will continue be installing traffic electrical conduit (underground electrical pipes) at the intersection of Mount Auburn Street and Arlington Street.

Mt. Auburn St. Project: Traffic & Pedestrian Signal Work, Bus Stop Moves Back to Normal Spot

The City of Watertown provided the following information about the Mt. Auburn Street Project. Update:  The bus stop for Route 71 at Mount Auburn St and Bigelow Ave that was temporarily relocated will resume its normal location on Saturday April 5, 2025. For more details on Route 71, visit the MBTA’s schedules and maps. Intersection of Mount Auburn Street & Arlington Street Electrical Traffic and Pedestrian Signal Work

Starting Monday April 7, 2025 Newport Construction will be installing traffic electrical conduit (underground electrical pipes) at the intersection of Mount Auburn Street and Arlington Street.  

Traffic ImpactsTemporary lane shifts may occur and work will take place on the sidewalks, but will remain open and accessible.

Weekend Work, Drainage Work, Traffic Signal Installations, and More on Mt. Auburn St.

The City of Watertown provided the following update about the road construction project on Mt. Auburn Street:

Weekend Work – March 8, 2025 – Pedestrian Signal Electrical Work

Saturday, March 8, 2025 Newport Construction and the City of Watertown will be performing electrical work to relocate pedestrian walking signals to prepare for signal preparation work at the Mount Auburn Street and Arlington Street intersection (see map below)

Traffic ImpactsTemporary lane shifts may occur and work will take place on the sidewalks, but will remain open and accessible. Parking ImpactsNo parking impacts

Drainage Installation Work Continues between Arlington St. and Bigelow Ave. Newport Construction is continuing to complete the drainage installation work eastbound between Arlington Street and Bigelow Avenue.

Mt. Auburn St. Roadwork Resumes After Week’s Delay for Weather

The following announcement was provided by the City of Watertown:

After work was paused the week of February 17-21 due to the weather conditions, the previously announced work will resume on Monday, February 24, 2025. Drainage Installation Work Continues between Arlington St. and Bigelow Ave. Newport Construction is continuing to complete the drainage installation work eastbound between Arlington Street and Bigelow Avenue and westbound between Arlington Street and Kimball Road. You can expect to see construction crews in this area from 7am to 5pm.

Mt. Auburn St. Project: Drainage Installation Work at Arlington St. & Bigelow Ave. Continue

The following announcement was provided by the City of Watertown:

Newport Construction is continuing to complete the drainage installation work between Arlington Street and Bigelow Avenue on the eastbound side. You can expect to see construction crews in this area from 7 a.m. to 5 p.m. during the week ending on Feb. 7, 2025. Traffic Impacts

There will be lane shifts and a potential lane closure during this work, which may also impact street parking in the immediate work area. Currently we do not anticipate any detours.

Watertown to Fund Temporary Paving of Mt. Auburn Street

The following update about the Mt. Auburn Street project was provided by the City of Waterotwn:

Temporary Paving Expected to be Completed Next Week

The City of Watertown has initiated work to temporarily level and pave the remainder of Mount Auburn Street next week while we await the completion of the Mt. Auburn Street Project. Originally not anticipated to receive any temporary paving as part of the project, the City has stepped in to fund this work to ensure one of Watertown’s busiest roads is paved for safer, smoother travel in 2024 ahead of the winter season. This work is being accelerated beyond the scope of the ongoing Mt.