Schools
Work Moving Ahead on New High School, Likely to Extend Into the Evening Some Days
|
The steel frame of the gymnasium at the new Watertown School before the slab is placed on the area in early April. (Courtesy of Vertex)
The following announcement was provided by Watertown’s project management firm, Vertex:
The new WHS Project Site remains busy as the site preparation and steel detailing continues. Above is a current view of the steel erection progress (view of the new gymnasium space) ahead of our upcoming slab on deck placement in this area next week. We have several slab placements on the schedule for next week proposed for the following dates:
Monday April 1st : Gymnasium
Wednesday April 3rd
Thursday April 4th
These slab placements are beginning at 7 a.m. on each of the above dates. The duration required for the slabs to be finished is dependent on the outside air temperate and weather conditions on the day of placement.